Backups taking twice as long
Hi,
I will give you the setup first then will try to explain my issue,
external hp ultrium 920 connected to a Smart Array Controller P212 in a HP ProLiant DL380 G6, running vmware esxi 5.0, with 2 windows 2008 R2 servers, one is the DC/FS/Exch and the 2nd is the sql server running a document manangement server.
What is happening is the time to do the backup job has almost doubled what it was doing before for the same amount of data
The time on average now is about 3 hrs(job rate 2247MB/Min) when before it was about 1.5 hrs(1262MB/Min) on average. Average byte count is about 210GB.
Now what happened was the tape drive failed(failed writing to tape) so we got it replaced and thats when the customer noticed that the jobs are taking longer.
The configuration is exactly the same setup as before the drive was replaced.
I did look at the job histories from before and after the drive was replaced and it looks like its taking longer to backup the main server, but there has been no major changes at all to the server configuration or software