Hi Guys,
Any ideas what might be going on here…
So I come in this morning and the backup from last night is still running. It is saying not enough disk space on the USB Drive.
I go to the USB Drive and check out the backup sets on the drive. There is a backup set there from the 12/04 which has a expiration date of the 19/04 (It is the 20/04 today in Australia, for those who are reading this elsewhere). So what it looks like has happened is the Backup Set is still protected even though the date said it shouldn't. The only thing I can think of is the system date of the machine is incorrect, but I checked that and it is set correctly.
Is there anything that I can try that you guys can think of?
Thanks in Advance
Peter
Just for info of others and bear in mind this still needs confirmation as this may not be the cause of Peter's problem
DLM will not groom the last complete recovery point chain (i.e. full + Incrementals) for a given resource as such if the set that appeared to have expired was part of the last recovery point chain then it will not be deleted with the result that you may run out of space if this has not been planned into your storage strategy.
Please see this blog
https://www-secure.symantec.com/connect/blogs/data-lifecycle-management-be-2012