Elapsed Time increase, Job Rate reduction and more tapes required

Our last two full backups, which run every Friday have suddenly increased in Elapsed Time and reduced Job Rate (our differential look fine), to the point that their running into Tuesday Morning for Verify (usually verify finishes early Monday AM).

There have been no changes (even if there was I would expect to see the differential reported differenty) to the server OS that I can see.

Also, the byte count compared to one of late July is the same (file count and area size aren't that different) but it now requires two additional tapes (800gb/1.6tb).

The only obvious observation is maybe a tape clean will help but any other thoughts on these additional times and tapes required?

I can see the Compression Ratio is 1:1 but two additional tapes and no apparent byte increase is not logical