VBS stastus question
Hello,
I have a quick quesiton regarding VBS. After we create tthe VBS, we setup the dependencies, if we setup the SG1 depend on SG2 and SG2 depend on SG3 and if we start VBS and if there is any issue with SG2, can we make SG2 to skip and bring SG1 up? Is there an option on VBS?
Hi,
VBS is just a virtual container ... no such option to my knowledge from VBS.
The status of group would depend on type of dependency between the groups ... if the dependency is hard/firm, & if SG2 is not coming up, you would need to resolve issue on SG2 OR you need to unlink the dependency in order to bring SG1 up.
G
This feature is not configuragble in the VBSs. You can look into the Recovery Plan feature for this capability (Chapter 23).
Veritas ™ Operations Manager
Management Server 6.1 User
GuideSee the Timeout value in the following sections:
See “Creating recovery plans” on page 408.
See “Editing recovery plans” on page 412.
See “Deleting a recovery plan” on page 416