Monthend_Full Backup not started as per schedule but manual backup completed.
Hello Guys,
my monthend full backup not started as per schedule. I think below is the reason for this but not sure i am right or not. Please share your opinion on this.
i have 2 schedule for a policy. 1 is full backup and will run on week-1,2,3,4 Friday 16:00. Its running fine asual.(calendr-include list)
Second schedule is Monthend_full, which is also full backup -evry last Friday 16:00. its not started for January month.(calender-include list)
I believe for this is Week4-Friday as per first schedule and Mothend_full schule also same days, JAN 26. So, due to this first schedule started and second monthend schedule was missed. Am i right?
Please share your thoughts and recommendations to avoid this in future for my envirornment.