Forum Discussion

nbuengr's avatar
nbuengr
Level 5
10 years ago
Solved

NetBackup POC

Hi, 

We are planning to do a POC with one of our customers. Is it possible to conduct a POC with an 8-core (single proc) CPU master server? 

We can provide at least 32GB RAM

Thanks!!

  • There is sizing advice in the "Symantec NetBackup Backup Planning and Performance Tuning Guide Release 7.5 and Release 7.6"

    http://www.veritas.com/docs/000004178

4 Replies

  • Form my point of view: 

    It depends on what exactly you want to POC: performance or functionality?

    If functionality - yes, go ahead.

    If performance - go through the Planning and Performance guide to ensure best possible environment.

  • Its fine, however, NetBackup prefers socket over cores. So if you have 8 cores, NetBackup would have the following preference from best to acceptable

    4 x Dual Core

    2 x Quad Core

    1 x Octa Core

  • There is sizing advice in the "Symantec NetBackup Backup Planning and Performance Tuning Guide Release 7.5 and Release 7.6"

    http://www.veritas.com/docs/000004178