12-05-2012 03:53 AM
Hi everybody!
I had have conflit with BE2012 and Veem (Application for Replication).
The problem occcurs for VMs servers (VMWare). I belive that the problem is happening because the BE2012 and Veem try to do a snapshot in the same time.
Look the error:
Backup- VMVCB::\\vcentersa.amer-s.tycoelectronics.com\VCGuestVm\(DC)BR506: Braganca Paulista, SP(DC)\vm\Windows Server 2008\br506ts17.amer-s.tycoelectronics.com
V-79-57344-38308 - The Virtual Machine resource is not responding. Backup set canceled.
Backup- VMVCB::\\vcentersa.amer-s.tycoelectronics.com\VCGuestVm\(DC)BR506: Braganca Paulista, SP(DC)\vm\Windows Server 2008\br506ts05.amer-s.tycoelectronics.com
V-79-57344-65304 - The Virtual Machine resource is not responding. Backup set canceled.
Somebody use Veem and BE2012?
Thanks,
Bruno Banfi
12-05-2012 04:02 AM
Hi
First of all its never recommended to have 2 backups from different applications run at the same time
We always recommend to have different schedules so that the jobs dont conflict
Thanks
12-05-2012 04:22 AM
So the first application (BE) we use only for backups and the other one (Veem) we use for replication for the other site (Brazil - USA).
I need to have this two application. I'll try to run in different time.
Thanks
12-12-2012 08:29 AM
12-12-2012 05:18 PM
See this document
http://kb.vmware.com/selfservice/microsites/search.do?cmd=displayKC&docType=kc&externalId=2014339&sliceId=1&docTypeID=DT_KB_1_1&dialogID=537538382&stateId=1%200%20537556639