02-05-2013 02:14 AM
I want to setup backup jobs to do Full and Incremental backup to backup data to disk and deplicate data to tape.
Can I setup backup job to deplicate backup data immediately after both full backup and incremental backup finished to backup data to disk?
When configuring the schedule setting of backup job, it seem to able to select either full backup or incremental backup only to duplicate to tape ? Both cannot.
Solved! Go to Solution.
02-05-2013 02:23 AM
You have to add a duplicate stage to both your full and incremental backup jobs.
02-05-2013 02:23 AM
You have to add a duplicate stage to both your full and incremental backup jobs.
02-05-2013 02:24 AM
You can refer to this link -
https://www-secure.symantec.com/connect/forums/can-i-duplicate-full-and-incremental-data-immediately-after-source-task-completed