Hi,

I have one job that backup 10 vmware virtual servers incrementaly daily every night and full backup on friday. On Saturday, this job duplicate latest full data to Tape.

Is there any option to add additional incremental backup ONLY for 2 servers (from my 10 server), that will run ADDITIONALLY twice a day and the backup will rely on my full backup?

I would like my full backup and tape backup to continue running as usual.

1 REPLY 1

pkh
Moderator
Moderator
   VIP    Certified
No. Not if you use the same job.