10-16-2012 05:37 AM
Hi,
I have a BE12.5 server in a branch office. When the weekly job runs, it doesnt get completed and the tape ejects automatically. So when i see the status of the job, it says the following:-
Completed status: Canceled, timed out The job was automatically canceled because it exceeded the job's maximum configured run time. |
How do i configure the job so that it completes the write operation to tape.
Thanks,
10-23-2012 12:42 AM
I tried the job again and the same thing happens. Its very strange that the tape is ejecting out and the job history says cancelled.
The job log says this:
|
Job Completion Status |
---|
Job ended: 22. oktober 2012 at 20:46:51 Completed status: Canceled, timed out The job was automatically canceled because it exceeded the job's maximum configured run time. |
Errors |
---|
Click an error below to locate it in the job log
Backup- G: Media mount failed. User canceled a Physical Volume Library operation. V-79-57344-33861 - The media operation was terminated by the user. |
Thanks!
10-23-2012 01:43 AM
Have you seen this technote?
http://www.symantec.com/business/support/index?page=content&id=TECH136105
Are there any messages in the eventlog between 22.10.2012 18:00 and 21:00 ?