02-29-2016 01:53 PM
I have a central admin server and 2 media servers can each server be configured to run a set of VM's from the same Vcenter Server or do the other 2 have to wait for 1 to complete?
Solved! Go to Solution.
03-01-2016 08:31 AM
I think this was licensing issue, as I placed the licenses on the CAS server defined a couple of test jobs and tried to run it; The CAS server started fine and my DMZ media server, sat waiting. It finally error'd out that it was not licensed for the operation.
Added a couple of the licenses to the DMZ server and both ran concurrant. FYI. Each media server is handling it own Datastore so contention should not be an issue.
Thanks for the responses.
02-29-2016 04:11 PM
02-29-2016 10:08 PM
Might be better to have 1 server run multiple jobs, preferably with VMs on different datastores to prevent multiple snaps of 1 datastore.
You could use the other server as in a DR-type scenario where you replicate backups too if needed.
Thanks!
03-01-2016 08:31 AM
I think this was licensing issue, as I placed the licenses on the CAS server defined a couple of test jobs and tried to run it; The CAS server started fine and my DMZ media server, sat waiting. It finally error'd out that it was not licensed for the operation.
Added a couple of the licenses to the DMZ server and both ran concurrant. FYI. Each media server is handling it own Datastore so contention should not be an issue.
Thanks for the responses.