04-21-2010 07:56 AM
04-21-2010 11:56 PM
Perform the following steps
1. Create a full backup Job and schedule it to run on every saturday or as per your need
2. Created duplicated --- In Job set up you can see the this option to create a duplicate job ---select the option to Duplicate backup set for the existing Job .
So this way after the original scheduled job completes it will start the duplicate job immediatly
If you want to sechedule the duplicate job to run at some specific time you would need to configure the job via policy
Which would have the following two template
1. Full backup job
2. Duplicate backup Job
Hope this information helps
04-23-2010 02:27 AM
Any update on this !!!
04-30-2010 11:06 AM
04-30-2010 01:10 PM