My tape drive manufacturer recommends that I clean my drive every X hours of drive use. Is it possible to schedule a cleaning based on this, or do I have to calculate approximately how many hours the drive is used per week, and then schedule based on that?

(example: cleaning is recommended every 150 hours, my average week uses 50 hours, so I need to schedule every 3 weeks)

the problem with the above scenario is that on weeks where my monthly/yearly backups run, the hours of drive use will be much higher than my average.
2 REPLIES 2

Sagar_Kamat_2
Level 6
Thank you for submitting this support query. There is no specific way to tell Backup Exec to run a cleaning job after X hours of backups. However, you can schedule a cleaning job to run every 3 or 4 days, if the backups are so frequent.


NOTE: If we do not receive your intimation within two business days, this post would be assumed answered and archived

Madhuri_Shenoy
Level 6
As per our previous reply, marking the case as "assumed answered" and moving it to "answered questions" pool.