Tape deduplication stopping scheduled

GaryGlover
Not applicable

I have setup a large backup job, in BE15, to backup all VM's in my enivornment to disk storage, doing a weekly full and daily differential. The weekly full runs over the weeked and then starts a duplicate to tape(which takes around 3 days to complete).

During the backup to tape the backup task is unable to run the daily deduplication because it is waiting for the 'related' tape job to complete.

Is there any way of seperating the tape duplication job so that the daily differential can run whilst the tape job is completing?

 

Ideally I don't want to split the job into multiple jobs that can complete within a day.

1 REPLY 1

Steve_4
Level 4

If you select a schedule instead for the task under the duplicate to tape job, you can choose when to run the duplicate to tape and make sure (Based on previous runs) that the weekly full completes before your scheduled duplicate.

Kind Regards,
Steve