β09-30-2013 02:09 AM
hi ,
i have a serious problem in my backup media set and i have to know how to solve it;
i have tow bakup job and they are assigned to my tape library
Backup_Sql with media Set of 1 week OPP (overwrite protection period) and infinite AP (append period) ==> tape1
Backup_Oracle with mediaSet of 1 week OPP (overwrite protection period) and infinite AP (append period) ==>tape1
i have assigned the tape 1 to a scratch media (manually),and the first backup Backup_Sql work with fine (and the tape 1 change properties from
scratch to 1 week OPP ) but the second fail with this error
Please insert overwritable media into the robotic library using the import command.
Overwritable media includes scratch, blank, and recyclable media. Please note that depending on the current Media Overwrite Protection setting, imported and allocated media may be overwritable as well. Consult the online help for more information on overwritable media.
i have to say that my tape has 1.5 Tb and the backup data of the tow set is about 10 Gb?
really i m confiused because there is a very large free space and the AP is put on infinite and the second job shows this error ????
please help
Solved! Go to Solution.
β09-30-2013 08:52 AM
β09-30-2013 02:25 AM
What is the job configuration? Is it set to Append to Media or Overwrite? When did both the jobs run?
β09-30-2013 02:49 AM
thanks to response
yes it is set to append , and it is a duplication job ,my tow job run every day at 18:00( sql) and 20:00 (oracle)
β09-30-2013 03:02 AM
So if I understand you correctly, are you wanting to put the duplication job on the same tape as the main job? This is not possible as it totally defies the purpose of duplication.
β09-30-2013 03:14 AM
No sir ,
i have for every job i have created a backup2disk then i duplicate to tape (another stage)
backup sql ==>disk (1 week OPP + inifinite AP)==>duplication2 tape(1week opp+infinite App) TAPE1
backup oracle==>disk (1 week OPP + inifinite AP)==>duplication2 tape(1week opp+infinite App) TAPE1
β09-30-2013 03:23 AM
Sorry I missunderstood. So I am now assuming both the duplicate jobs are using same media set. Make sure that duplicate 1 and duplicate 2 start times are not overlapping. What I mean is Schedule your 2nd duplicate job in such a way that that the first duplication has completed.
Edit:
See point 4 in this blog written by the Trusted advisor pkh
https://www-secure.symantec.com/connect/articles/why-my-job-not-appending-data-my-tapes
β09-30-2013 03:40 AM
but in my case there are totally separte ( with about an hour ) and also i have one tape drive
so an overlap is impossible .
but this point is very starnge :
β09-30-2013 04:02 AM
Point 2 is not applicable in your situation as it is only in situation where Backup job needs to span tapes. In your situation, the Tape capacity is about 1.5TB and the job size is 10 GB.
β09-30-2013 04:13 AM
ok man ,
so what should i do ?
β09-30-2013 06:51 AM
have you a Tape-Autoloader or Tape-Libary or a single Tape-Drive ??
β09-30-2013 07:01 AM
i have a tape -autoloader with one drive.
β09-30-2013 07:05 AM
have you ever thought about Configuring Tape-Partitions ?
β09-30-2013 07:59 AM
yes ,i have already 7 tape partitions but there used by other jobs( evrey tape has one job configured) only tape 1 that i used for duplicating the SQL and the Oracle database.
β09-30-2013 08:52 AM
β10-01-2013 12:34 AM
but in my case there are totally separte ( with about an hour ) and also i have one tape drive
so an overlap is impossible .
No. This is not true. By overlap, I mean that the first job is running when the second job starts. Make sure that your first job finishes before you start the second job. Otherwise, your second job may go into overwrite mode and thus will be unable to append to the tape.