11-08-2018 03:40 AM
Hi, appreciate the clarification again. Can you run another backup job (differential backup let's say) while a backup job running D2D2T duplicate to tape is still running? Does the job running the duplicate to tape have to complete (end) in order to run another job to take the differential backup from the same source?
11-08-2018 08:09 AM
As far as I am aware, if any part/stage of a backup definition is active then no other part/stage of the same definition will run.
11-08-2018 08:17 AM
Thanks for the reply. I might have to try this out when I get the time.