Hi,

Can anyone help me to setup the Enterprise vault DR site.

Primary site

Exchange 2010 with DAG.

We are implementing the Enterprise Vault 9.0.1 server in Windows cluster environment.

The SQL server will be a standalone server.

DR site.

Exchange 2010

At DR site we have standalone server for Enterprise vault & For SQL server.

The Replication of Data is SAN Based.

So my query is that to implement the DR site for Enterprise Vault what steps I need to take at DR site?

 

Regards,

Rohan.

1 Solution

Accepted Solutions
Highlighted
Accepted Solution!

Have a read of the

Have a read of the Administrators_Guide.pdf, there is a section in there for DR.  You would probably want to go with the Data Only DR steps.

https://www.linkedin.com/in/awsterling/

View solution in original post

5 Replies
Highlighted
Accepted Solution!

Have a read of the

Have a read of the Administrators_Guide.pdf, there is a section in there for DR.  You would probably want to go with the Data Only DR steps.

https://www.linkedin.com/in/awsterling/

View solution in original post

Highlighted

@ Tony What about using

@ Tony

What about using USL?

~USL is still in the same guide I believe

Highlighted

USL is in the guide but you

USL is in the guide but you would need to have the EV Server as part of the site.  I think USL is great for failover of an EV server in a site but not a complete DR from one site to another.

https://www.linkedin.com/in/awsterling/
Highlighted

Hi Tony can you please tell

Hi Tony can you please tell pe the page no of DR section, coz I am not able to find it in Administrator_Guide.

Regards,

Rohan.

Highlighted

In the EV 9 Admin guide it is

In the EV 9 Admin guide it is Chapter 24 titled Recovery.  Page 335.

 