01-22-2020 09:33 AM
I updated the Host Properties Master setting of Jobs per client from 4 to 6.
Its been 24 hours, i still have jobs waiting with message -
Limit has been reached for the logical resource Master.NBU_CLIENT.MAXJOBS.Client
I did the usual, bprdreq -rereadconfig, nbpemreq -updatepolicies but not sure if those are related to the Master Host properties refresh. Any pointers?
Solved! Go to Solution.
01-22-2020 11:51 AM
01-22-2020 11:51 AM
01-27-2020 07:32 AM
Ok. Thanks.