10-26-2018 06:38 AM
Hello friends!
Do you know if there is any way to limit the number of jobs when replication starts?
Best Regards.
Solved! Go to Solution.
10-26-2018 06:41 AM
Yes, you can control number of jobs through Maximum Concurrent Jobs on Storage Unit that you are using for the replication or Max I/O Streams on the disk storage pool that is configured for replication.
10-30-2018 08:27 AM
Thanks, I've changed Max I / O and everything and everything is ok now.
10-26-2018 06:41 AM
Yes, you can control number of jobs through Maximum Concurrent Jobs on Storage Unit that you are using for the replication or Max I/O Streams on the disk storage pool that is configured for replication.
10-26-2018 08:17 AM
Hello,
Kindly refer below mentioned article for tuning replication for the better outcome
https://www.veritas.com/support/en_US/article.000095103
Regards,
10-30-2018 08:27 AM
Thanks, I've changed Max I / O and everything and everything is ok now.