Which log to see scheduled jobs start?

Nathan_Kippen
Level 6
Certified

I know that nbpem builds a work list of due jobs on the master server.  It builds the list of scheduled jobs from data provided by bpdbm.  When a job is due nbpem sends a job try for each due job to the nbjm process.  nbjm notifies bpjobd to add the job to the jobs database, and the job appears in the activity monitor.

The unified logs for nbpem show when jobs finish .. the unified log for nbjm shows details during the job duration ... which logs captures the initialization of a job that is due to run?

The other day I noticed that scheduled jobs were not being kicked off.  I ended up having to recycle netbackup to get things working again.  I saw nbpem logging data through this time frame... but was there still a part of nbpem that was hung up?  .. I'm trying to determine when my problem began.

Thanks,

2 REPLIES 2

rjrumfelt
Level 6
that could be your problem.  What version of NBU are you running?

I know 6.5.2A had problems with jobs not kicking off when they were scheduled.  We had to get an EEB installed to correct the issue.

Nathan_Kippen
Level 6
Certified

Master:

HP-UX IA 11.23
NB Enterprise 6.5.5