12-06-2016 11:02 PM
Hi techies,
Can anybody help on the following requirement:
We Have 2 sites A & B which individually having a Netbackup master server & OPS center Sever.
Now we want to remove Site-B ops center intead of this we want to use Site-A ops center for reporting of both Netbackup Servers of Site-A & Site-B.
Based on this requirement we have the following querys:
1.Can we add site-B OPS Center db data to Site-A OPS Center DB Such that we can get the historical data also.if posssible may i know the procees or supporting links.
2. If '1' is not possible, if we add Site-B netbackup master server to Site-A OPS Center for reporting is there anything we need to Change in the Hardware or Software of OPS Center server of Site-A.
Netbackup Version is:7.7
OPS Cneter ver:7.7
Platform:windows 2012 R2 Standard.
Solved! Go to Solution.
12-07-2016 10:14 PM
Merging 2 opscenter dbs is not possible considering there are ids each entity gets in opscenter db and 2 diffrent dbs might have same entity ids which would cause inaccurracies if merged.You may just add the new server ( from Site A) to existing OC server (on site B) and keep the old OC server ( on site A) just for historic report.
Deeps
12-08-2016 10:26 PM
You may refer to Opscenter Performance and Tuning guide (Sizing considerations) to make sure your current server can accomodate the new server . Basically it depends how many master servers you add, how many jobs run every day , number of policies, numberof images ,how many schedule reports you have among many other factors.
It is also advisable to keep you Opscenter on the highest level , so depend upon the version of master server you might need to upgrade opscenter server.
Thanks
Deeps
12-07-2016 10:14 PM
Merging 2 opscenter dbs is not possible considering there are ids each entity gets in opscenter db and 2 diffrent dbs might have same entity ids which would cause inaccurracies if merged.You may just add the new server ( from Site A) to existing OC server (on site B) and keep the old OC server ( on site A) just for historic report.
Deeps
12-07-2016 11:47 PM
Hi Deeps,
Thanks for the reply.
One more is there nay need in the software or harware in Site-A OPS Center server while adding Extra Netbackup master server for reporting.
12-08-2016 10:26 PM
You may refer to Opscenter Performance and Tuning guide (Sizing considerations) to make sure your current server can accomodate the new server . Basically it depends how many master servers you add, how many jobs run every day , number of policies, numberof images ,how many schedule reports you have among many other factors.
It is also advisable to keep you Opscenter on the highest level , so depend upon the version of master server you might need to upgrade opscenter server.
Thanks
Deeps