04-22-2015 01:13 PM
All
I was testing SSR 2013 R2 on a virtualized Windows 7 workstation. As the backup destination I added another virtual drive and configured a backup schedule which worked fine creating the first base image and then incremental images with consolidation as well.
Then I detached the vitrual disk used as the backup destination , added it to another VM and used SSR recovery cd to test restoration to dis-similar hardware which worked fine as well.
Once the tests were done I detached from the test VM and attached the backup destination virtual disk back to the original windows 7 vm and SSR detected that few backup schedules were missed so it wanted to start the backup job.
Once the backup is started it created a completly new base image and incremental backups insted of using the existing base image.
Is this normal behaviour ?
Thanks,
Dhanushka
Solved! Go to Solution.
04-22-2015 11:03 PM
Yes it is.
04-22-2015 11:03 PM
Yes it is.
04-24-2015 07:10 AM
Thanks for the confirmation Markus.