Forum Discussion
CraigV
Moderator
You should be looking at separating the Verify job from the actual job itself. There is a setting in BE 2010 R3 for this. It means your backup job will complete, and only then will the Verify job run. Thanks!
joeyiu
7 years agoLevel 3
Dear CraigV,
Thanks, I have created a new data verify job to try, my question is, as I have to select the resources according to backup date (attached), is that mean I have to revise the selection manually everyday instead of making it a recursive one?
thank you.
Joe