I've a backup policy that makes use of the Calendar Schedule feature of NetBackup 7.0, running on RHEL 5.2. The schedule is set to run only on the last day of the month. However, everytime I check the policy a few days later, I noted the schedule reverted to its original setting, where first day and last day of the month, and weekends are also checked. This resulted in my backup job running on days other that the last day of the month as intended. This have been confirmed to be a recurring issue and I've confirmed that no one is tampering with the policies.
Any idea what could be causing my backup policy calendar schedule to reset? Is there something else I need to configure beside the obvious settings in the policy tabs?
- can you try to disable the policy,and create a new policy instead.