Vmware Backup D2D2T
HI Guys,
I am trying to setup a vmware disk-to-disk-to-tape backup stratergy. We have approx 1tb of virtual machines to backup which i would like offsite to tape. The main concern is the amount of time to backup. We have a time window of approx 8 hours overnight to disk, then the tape backup can run from the backup server at any time
The infrastucture consists of the following
- 2 x Vmware 5.0 hosts
- 1x Equallogic
- 1x LTO 5 Tape Drive connected via sas 6gb/s
- 1x Backup Server running Symantec Backupexec2010 R3 with all licenses required.
I believe what I am trying to achieve would be a backup to disk policy then to tape. My only problem would be getting the entire backup to the tape for dr purposes.
What are the best ways of getting the results I am looking for? Would we need to incorperate incremental or differential backups to tape only?
Regards