Forum Discussion

sandrine_goetha's avatar
6 years ago

CAS Server

Hello, We noticed this morning during the synchronisation run of all the  Ev servers, that one  CAS( Exchange 2010) server was up to 100 % for few minutes.We looked and realized that all the tasks a...
  • GertjanA's avatar
    6 years ago

    Hello Sandrine,

    I'm not sure that is possible, but will try to find something. To 'fix', how about you change the tasks schedule to sync? You could then define each task to sync at a specific time, to lower the burden on the CAS server.

    Instead of running them all at 12/24, schedule tasks per server 1/13, 2/14 etc.

    You need to use MSMQ to see when the sync finishes:

    The Synchronization process will be managed by the Enterprise Vault Exchange Task for <ExchangeServerName>  A7 Queue (for Enterprise Vault 8.0 and later). Once the A7 Queue has returned to 0 items, the Synchronization process has completed.  

    If and when I find additional info, I'll let you know.