Hello All
NBU master+media all at 7.6.0.1 I have close to around 50 policies. all of them have calender schedule for yearly backups. I need to verify their annual calender schedule. It should have...
- 10 years ago
A bppllist or bpplsched (with -L) will give you something like this for calendar-based schedule:
Calendar sched: Enabled
Allowed to retry after run day
Included Dates-----------
Monday, Week 1
Monday, Week 2
Monday, Week 3
Monday, Week 4
Monday, Week 5
Excluded Dates----------
No specific exclude dates entered
No exclude days of week enteredBut it won't give you the exact date as this is calculated internally by nbpem. As SymTerry pointed out, the nbpemreq predict can give you the next (calculated) run date.