OldEmployee
7 years agoLevel 5
Schedule Archiving tasks do not complete
The tasks are scheduled to run 6 AM - 12 PM and 1:30 PM till 12 AM daily.
However, some of the schedule tasks just show as running in the report mode even past the end schedule.
New scheduled run will begin while the older is still active.
Even after I stop and start the task, the report shows the schedule run as running.
Is this because of the schedules or is something else affecting the run time?
Hi Patrick,
Thank you.
I played around with the scheduled task settings (connections, number of items) and have been monitoring the tasks for a few days. They are working as expected now. The start and end on the scheduled times as expected.