calender scheduling

Hi ALL..   I have a request from client to run the backup a 6 in evening to 2 in night(spans midnight) on 10 and 11 march 2013. I have set the calender schedule.NBU 7.1   My calender schedu...
  • RamNagalla's avatar
    12 years ago

     

    below lines from the admin guide will answer your question.. 
     
    A backup window may begin in one day and end in another. If this kind of policy
    is scheduled to run each day, NetBackup does not run the job again immediately
    after midnight. Instead, even though the window spans into another day,
    NetBackup considers it to be one window. NetBackup recognizes that the
    administrator’s intention is usually not to have a job run again so soon after the
    previous backup.