Andy2345
12 years agoLevel 6
calender scheduling
Hi ALL..
I have a request from client to run the backup a 6 in evening to 2 in night(spans midnight) on 10 and 11 march 2013.
I have set the calender schedule.NBU 7.1
My calender schedu...
- 12 years agobelow lines from the admin guide will answer your question..A backup window may begin in one day and end in another. If this kind of policyis scheduled to run each day, NetBackup does not run the job again immediatelyafter midnight. Instead, even though the window spans into another day,NetBackup considers it to be one window. NetBackup recognizes that theadministrator’s intention is usually not to have a job run again so soon after theprevious backup.