New incremental backup job appears to be running as full backup

Matthew_Sweitze
Not applicable
I created a new incremental backup job using time stamp option. I assumed the job would use the last full backup as the job from which to run the new incremental job. But it appears to be running a full backup, albeit very slowly.

Why would it not use the last full backup as the base for this new backup job?
1 REPLY 1

Amruta_Bhide
Level 6
Hello,

Do your full backups also run with the changed time stamp option? The Incremental/diffrential backupes take a Q from the Full backup. >If your Full backup is running with Archive bit option, your Incremental will not run with time stamp Option.

Hope this helps you.

******************************************************************
*****************************************************************

Note : If we do not receive your reply within two business days, this post would be marked ‘assumed answered’ and would be moved to ‘answered questions’ pool.