how to do week 5 full Last Friday runs only on Months that have only 5 Friday scheduled jobs

MEL-Masry
Level 1

The scenario that I create scheduled Jobs

5 full weeks taps run on Friday.

6 day's differentials taps run every day.

how to do week 5 full Last Friday runs only on Months that have only 5 Fridays.

I tray two jobs and they giving the same start time as week 4

image.png

  • Months >> Every last Friday of every 1 month.
  • Months >> Selected Days of the months & including Dates 
  • image.png
  • Scheduled DatesScheduled Dates

 