10-03-2011 11:47 PM
Hi,
Recently I came across a backup job which get stuck and couldnt complete after 18hours.
I would like to know how can I configure the job to terminate itself automatically if the job cannot
complete after 10hours. ( I am confident that the job should complete within 1-2 hours max).
Using Backup Exec 2010 R3
Thanks
Solved! Go to Solution.
10-04-2011 12:01 AM
In the backup job window, check the "Availability & Priority" option there you will find "Enable
Automatic Cancellation" option
10-04-2011 12:01 AM
In the backup job window, check the "Availability & Priority" option there you will find "Enable
Automatic Cancellation" option
10-04-2011 02:51 AM
Wouldn't it be more prudent to find out why the job is taking 8 hours longer than it should?
More often than not, I find that rebooting the source server fixes the issue or that it shows me an issue on the source server that is lurking and waiting to fail.
10-04-2011 11:57 AM
Agreed you should really look into why the backup is taking so long rather than just making the error disappear.