Prasad V wrote:
I have to manually start them.
The frequency is determined by when the last full backup ran. If you are manually starting them then that would be the last full backup. If they are scheduled to run on Saturday with a frequency of 1 week, and if you run a manual backup on Monday because the Saturday did not run. Then a week will not have elapsed since the last full backup. There will only have been 5 days since the last full backup ran on Monday..
When the window opens on Saturday it will not schedule the backup because 1 week has not passed. Does this make sense?
Oh...substitute Friday night with Saturday in the above description. Basically change the frequency to 3 days instead of 1 week to prevent schedule creep.