10-04-2014 08:39 PM
I am running BE 2014 SP1.
After a backup I run two duplication jobs. I want to adjust the priority of these jobs.
I tried using the GUI to adjust the prority but this changed the priority of the backup job and left the duplication priority at medium. I want to adjust only the priority of the duplication jobs.
Is this possible, if so how?
Thanks
Solved! Go to Solution.
10-04-2014 09:35 PM
No. It is not possible to set the priority for a duplicate job.
Perhaps you would like to make case for this feature and add it as an idea in the Ideas section.
10-04-2014 09:35 PM
No. It is not possible to set the priority for a duplicate job.
Perhaps you would like to make case for this feature and add it as an idea in the Ideas section.
10-04-2014 10:05 PM
Thank you for your quick response.