Hi - I'm using Veritas v9.00 - Rev 4494. Every once in a great while, the backup will showup as Failed, and there is no elasped time - but the byte count is correct and looks like all the files backed up properly.

Under Job Completion Status - It says Canceled by service shutdown.

Under Erros - It says The media operation was terminated by the user. Canceled by service shutdown.

Yet - the backup works fine most days and no one cancelled the backup.

Thanks in advance for your help..
2 REPLIES 2

anoop_nair_2
Level 6
Hi,

We suggest you to upgrade to BE v9.1.

We would suggest you download and install it using the following technote's:


http://seer.support.veritas.com/docs/264658.htm

Abhinav_Bindroo
Level 6
Assuming the solution provided is correct. Also, there is no response from the customer within 2 days from the last reply by Veritas