It seems that when you schedule a report job to run at a specific time and attach the report to the email notification, it sends out the Crystal Reports *.rpt file instead of an HTML or PDF document. Also the report seems to contain no data.

Thanks.

Andrew
4 REPLIES 4

Brad_Willadsen
Level 3
This has been reported and fixed. Please install Hotfix #3 to resolve the issue.

http://support.veritas.com/docs/274404

Andrew_Storrs
Level 3
Thanks Brad.

Tim_Washburn
Level 2
The link is no longer active. Can you repost the correct link?

Andrew_Storrs
Level 3
It is now included in SP1.

http://seer.support.veritas.com/docs/275248.htm