Hi
We are decommissioning an MSDP and need to move the data to a Data Domain. It is logically about 250TB so we have kicked off parallel duplication jobs. The speeds are good considering; but no matter which way you look at it 250TB is a lot! [ Using boost over 10GB LAN ]
It doesn't seem like the jobs are running as optimised duplications (like MSDP to MSDP does), is this even an option for MSDP to Data Domain?
Thanks
Solved! Go to Solution.
11-12-2014 12:42 AM
Not possible between different manufacturers / storage types.
MSDP -> DD will rehydrate the data.
See:
About MSDP optimized duplication limitations
http://www.symantec.com/docs/HOWTO88990
11-12-2014 12:42 AM
Not possible between different manufacturers / storage types.
MSDP -> DD will rehydrate the data.
See:
About MSDP optimized duplication limitations
http://www.symantec.com/docs/HOWTO88990
11-12-2014 12:56 AM
Thanks Marianne