Hi,

we are using NetBackup 6.0 MP3 in a MS Windows environment.

I have the problem that apparently the staging schedule does not work automatically any more. Impact is that the staging unit reach its maximum capacity and no further backups could be performed till i use the manual relocation function. A little strange because in the past all works fine and i dont remember any change.

We have the staging unit configured as followed:

- On demand only
- Maximum Concurrent Jobs 15
- Low Water mark 20%
- Enable Temporary Staging Area

The Disk Staging Schedule is configured with a Frequency of 1 Hour at all days but in the activity monitor no dssu job appears :(

Some idea?

Thanks in advance,

Oliver
2 REPLIES 2

Oliver_Mohre
Level 3
No ideas?

Derek_Black
Level 4
I'd have a look in the bpdm and see what's happening. Usually it gives you some sort of output like why it's choosing the images to destage, etc.  Make sure you have verbosity set high.