1PSS wrote:Hi All,I have a question I can't seem to get around my mind..... using NB5.1.Say I run a Full on Sunday the 1st, and a cumulative incremental each on Mon. 2nd and Tues. 3rd.No changes were made on Monday, and some were made on Tuesday.If I run a bprestore and select the dates first through the third, why does it seem as though NB wants the tapes from the 2nd also, even though there are only empty folders on them?Does NB go through the motions of restoring the 2nd, and then lays down the 3rd afterwards?