Scheduled Policy End Time

Andrea_Francesc
Level 3
Partner Certified
Hi.
I've a scheduled policy that starts (Start Time) on Mon at 20:00 and will finish (End Time) Tue at 5:30.
Some times, job correctly finished over 'End Time' I've defined.
Is it the normal behavior for NetBackup, isn't it?

When 'End Time' parameter in 'Start Window' is used?
Need I to adjust 'Start Time' and 'End Time' to avarage time needed for the policy?

Regards.
3 REPLIES 3

Patrick_Whelan_
Level 6
The "end time" of the backup window is the latest time that a backup may START. Once a backup starts it will continue until it finishes. If you need the job to finish by the end time, you have to estimate the length of time the average backup runs and adjust the end time back this many hours. Hope this helps.
 

Andrea_Francesc
Level 3
Partner Certified
Yep, it helps. Smiley Wink
I cannot find this information in Netbackup docs.

Thank you so much.
Regards.

Jim_Horalek
Level 4
Partner Accredited Certified
It also means jobs that are part of another job will not start after the End Time.
You will usually see these jobs a queued. Suppose your backing up three clients. Each client is a job, you backed up client 1 and 2. The end time occurs, client 3 won't get backed up. Good news is client 3 is moved to the front of the list for the next backup.
 
JIm