i sceduled the policy on 10.30 to 7 but before that it was 8-4  but actualy it showing the previusly  new scheduled not run  i check the nbpemreq -update

and restart the NBU  policy is daily incremental   and my o/s is solaris  NBU  version is 7.0.1 so kindly give me all steps  i have to follow .....and why this happen .....

2 REPLIES 2

Nathan_Kippen
Level 6
Certified

run

bppllist <policy name> -U

post output.

Marianne
Level 6
Partner    VIP    Accredited Certified

Frequency or calendar based schedule?

Please post policy config:

bppllist <policy-name> -U

To update nbpem with new schedule info, use 'nbpemreq -updatepolicies'.