06-05-2014 10:33 AM
I had found an old thread asking this but there was no reponse.
Please could anyone explain the "Detail Job Type" field is displaying results such as 200, 600, and 1000.
I have been sent dome job reports but they seem to have multiple entries for hte same job. Maybe they are parent/child processes but it is driving my mad now knowing.
Any help would be appreciated.
Thanks
Andy
Solved! Go to Solution.
06-05-2014 05:52 PM
When running a report, ideally the "Detail Job Type" values should be translated from numbers to strings.
200 refers to backups, 600 refers to restores and 1000 refers to the verify operation.
06-05-2014 11:45 AM
just wondering if you change the default report type from HTML to Pdf, does that make a difference?
see pg704 of the Backup Exec 2010 Admin Guide http://www.symantec.com/docs/DOC4855
06-05-2014 12:42 PM
unfortunately not onsite any more. it seems strange that there is not a docuemnt that explains something so simple from a report.
06-05-2014 05:52 PM
When running a report, ideally the "Detail Job Type" values should be translated from numbers to strings.
200 refers to backups, 600 refers to restores and 1000 refers to the verify operation.
06-11-2014 01:04 PM
thank you VJware