My backups are scheduled to start running at 3:00 AM, not later than 3:04:59 AM.
However, according to my job summary it is not.
original start time: Saturday, April 09, 2005 3:00:00AM
job started : Tuesday, April 12, 2005 3:00:03AM
job ended : Tuesday, April 12, 2005 1:24:31PM
elapsed time : 10:24:28
When the backup is working correctly it should only take 45 minutes, that includes the verify.
When the operator comes in the office in the morning, 7:00AM, the tape has ejected itself, so she was assuming it was done. Later in the day, about 1:00PM, she would insert the next backup tape - it would run for about 20 minuntes and then eject itself again, which would explain the 1:24PM completion time.
Is the window of 3:00AM not later than 3:04AM to start not long enough? I thought that was just a start time, not a completion time.
Judy