I just want to know how it could be possible to stop a duplication job in a "Work in progress" state ?
In fact, this job seems to be unactive ...
This job has been runned on July 21st and nothing occured ...

If i try to delete it, i get the following answer : Unable to delete a work in progress job ....

Thanks for your answers
Best Regards
Olivier
1 REPLY 1

Renuka_-
Level 6
Employee
Hello,

When you right click on the job in job monitor you get an option to cancel the job, do this. If after this the staus changes to cancel pending do the following.

Try restarting all the backup exec services, if that does not work close the application and restart it. As a final resort if neither of these work please restart the server.


Additional Information :
For information on the recent VERITAS Backup Exec security vulnerabilities, including links to the downloads for the necessary hotfixes, please refer to the following document:
Patch summary for Security Advisories VX05-001, VX05-002, VX05-003, VX05-005, VX05-006, VX05-007

http://seer.support.veritas.com/docs/277429.htm

NOTE : If we do not receive your reply within two business days, this post would be marked assumed answeredand would be moved toanswered questions pool.