10-06-2008 02:36 PM
Hi,
I want to break down a large multi tape backup job into several smaller jobs, but I can't see any way to chain the jobs. I know I can create a policy with multiple templates but there doesn't seem to be a way for each template to run a job with a different selection list. Is there? I've created several selection lists to break up the job. Should I be breaking it up some other way? Or I do I have to schedule times and hope the windows are large enough?
Ideally I'd also like to run a cleaning job between tape changes.
Any help? Thanks
10-07-2008 09:34 AM
Or I do I have to schedule times and hope the windows are large enough?
You can do that, but the job timer will start as soon a the job is 'started' even if it waits for an hour for a drive to free up
You can also use the POST job command to run a BEMCMD job to release the next job in line
10-07-2008 09:45 AM
@ken Putnam wrote:You can also use the POST job command to run a BEMCMD job to release the next job in line
Hi,
Thanks for the reply. Using the POST job command looks like a good idea. Is there documentation for BEMCMD anywhere? Can it be used just to run a previously defined job?
10-07-2008 10:02 AM