Hi all,
 
I would like to create a schedule which basically involves 10 Tapes, which are exchanged on a weekly basis.
So one week would be stored on 1 tape using "Differential"..
 
The goal is to maintain an archive for 10 week period before overwriting the first tape again....
 
Any ideas how I can achieve this? I've tried but have not succeeded yet....
 
I'd be thankful for any hints tips´solutions... Smiley Happy
 
thx
 
Willie
1 REPLY 1

Ken_Putnam
Level 6
You would need two jobs, both using the same media set
 
Weekly Full Overwrite
Daily     Diff  Append
 
The media set would need APP of 6 days, OPP of 81 days