Schedule Problems.....

Andi_Taylor
Level 2
Hi Guys,

I was after a little help. I am currently trying to back up my Exchange server, Exchange 2003 running on a 2000 Server. Recently my job has begun failing with an access denied error. Trying to solve this i re-created the job however now i cannot schedule the job correctly. For instance if i set the effective date to 26/4/06 and submit the job it will always set the date of the first instance of the job to the 1st May!!! This is driving me insane, i have re-created the job several times, my regional settings are correct and the date and time are fine. Has anyone seen this before i really need help i haven't had a successful backup in three days!!

Thanks in advance
1 REPLY 1

Ken_Putnam
Level 6
You don't have the start time shortly after midnight, do you?