Scheduled backups for April 10, 16. Yet start time shows only 16th?

Howard_Chiu
Level 4
I have tried removing the dates, submitting the changes and re adding them.

However, it shows the starting dates to be the later date. It is the same for three separate backup jobs.
The backup jobs do not run, and I have to manually have them run.

Is there any option I have other than recreating the entire backup jobs?

These backup jobs were working fine for several months.

Thanks in advance!
3 REPLIES 3

Ken_Putnam
Level 6
Have you tried a Database Repair? 
 
 
Also, there were problems with scheduling in the early v11 code. 
Make sure you are on the latest Service Pack


Message Edited by Ken Putnam on 04-04-2008 09:57 AM

Howard_Chiu
Level 4
thank you very much for that suggestion. I will try both repair and updating and post back here with the results!

Howard_Chiu
Level 4
Ken,

Thanks again. I updated with SP1 and it did not seem to make any immediate changes.

I believe my issue was:
ETrack: 865804
Modifying a scheduled job twice causes the scheduler to skip the next scheduled backup

I then rebooted my machine and saw that the schedule was still wrong. I then went to "job setup" and was about to recreate all my backup jobs, but I decided to try "copy" first. The copied job had the proper backup schedule!