Veritas 10.0 Start another backup job after 1st one runs

Philip_Walker
Not applicable
I would like to run 2 backup jobs each night. The 2nd backup job needs append to first jobs tape after it completes. Hown can I do this? Is it post commands?
1 REPLY 1

Gauri_Ketkar
Level 6
Hi,

You want 2nd Job to be started when 1st finishes and append to the same tape?

Considering the time windows of first job you can schedule the second job with append to same device (media with correct media set)

You can also create a post job command to automatically start the second job.
http://support.veritas.com/docs/253162

Revert for any further queries.

Thank you

Additional Information :
For information on the recent VERITAS Backup Exec security vulnerabilities, including links to the downloads for the necessary hotfixes, please refer to the following document:
Patch summary for Security Advisories VX05-001, VX05-002, VX05-003, VX05-005, VX05-006, VX05-007

http://seer.support.veritas.com/docs/277429.htm



NOTE : If we do not receive your reply within two business days, this post would be marked "assumed answered" and would be moved to "answered questions" pool.